BASSnet Procurement - Query of (Requested Date, Required Date & Reply By Date)

1. Is required date is auto field ?

- This is the date when the goods where the order are required.
Yes, it will auto fill to today's date. User can change update the date later.

 

2. Is reply date auto / linked to required date or requested date ?

- This is date is for the purchaser to inform the vendor when the reply is required for this request for quotation. By default, it is today's date. Purchaser can modify the date.

- If you have set up the PO Priority in the Procurement register, then the date in this field will be automatically populated based on the Priority level selected for this Requisition. Let's say priority days for "Normal" is within 5 days. Hence, the reply by date will be on the 24th March 2025.

 

3. Requested date is the date when vessel created this Requisition ?

 - Yes, the requisition creation date. 